Generates a phased Modernization Brief from assessment artifacts, producing an approval-ready document with target architecture, migration sequence, and validation strategy.
npx claudepluginhub minhthang1009/dotclaude --plugin code-modernizationHow this skill is triggered — by the user, by Claude, or both
Slash command
/code-modernization:modernize-brief <system-dir> [target-stack]<system-dir> [target-stack]The summary Claude sees in its skill listing — used to decide when to auto-load this skill
Synthesize everything in `analysis/$1/` into a **Modernization Brief** — the
Creates p5.js generative art with seeded randomness, noise fields, and interactive parameter exploration. Use for algorithmic art, flow fields, or particle systems.
Share bugs, ideas, or general feedback.
Synthesize everything in analysis/$1/ into a Modernization Brief — the
single document a steering committee approves and engineering executes.
Target stack: $2 (if blank, recommend one based on the assessment findings).
Read analysis/$1/ASSESSMENT.md, analysis/$1/TOPOLOGY.html (and the .mmd
files alongside it), and analysis/$1/BUSINESS_RULES.md first. If any are
missing, say so and stop — they come from /modernize-assess, /modernize-map,
and /modernize-extract-rules respectively. Run those first.
Write analysis/$1/MODERNIZATION_BRIEF.md:
One paragraph: from what, to what, why now.
Mermaid C4 Container diagram of the end state. Name every service, data store, and integration. Below it, a table mapping legacy component → target component(s).
Break the work into 3-6 phases using strangler-fig ordering — lowest-risk, fewest-dependencies first. For each phase:
Render the phases as a Mermaid gantt chart.
List the P0 rules from BUSINESS_RULES.md (the ones tagged Priority: P0 —
money, regulatory, data integrity) that MUST be proven equivalent before any
phase ships. These become the regression suite. Flag any P0 rule with
Confidence < High as a blocker requiring SME confirmation before its phase
starts.
State which combination applies: characterization tests, contract tests, parallel-run / dual-execution diff, property-based tests, manual UAT. Justify per phase.
Anything requiring human/SME decision before Phase 1 starts. Each as a checkbox the approver must tick.
Approved by: ________________ Date: __________
Approval covers: Phase 1 only | Full plan
Enter plan mode and present a summary of the brief. Do NOT proceed to any transformation until the user explicitly approves. This gate is the human-in-the-loop control point.