From pm-skills
Generate a Project+ style change request as .docx — request metadata, description, impact analysis across scope/schedule/cost/quality/resources/risk, options considered, recommendation, and CCB approval block. Use whenever a user needs a change request, CR, change control form, scope change document, RFC, or baseline change. Triggers include "change request", "CR", "change control", "scope change", "baseline change", "RFC". Enforces never-invent discipline for impact numbers, CCB members, and disposition — and preserves the user's fuzzy estimates exactly.
How this skill is triggered — by the user, by Claude, or both
Slash command
/pm-skills:change-requestThe summary Claude sees in its skill listing — used to decide when to auto-load this skill
Draft-first: parse what the user gave, fill the schema, run the script. Only interview if the user explicitly asks.
Draft-first: parse what the user gave, fill the schema, run the script. Only interview if the user explicitly asks.
Change requests are high-stakes governance artifacts. Baselines of scope/schedule/cost only move through a formal CR, so the artifact needs to be auditable: every impact number traceable to the requestor, every CCB member named by the user, and disposition left blank until the user says a decision was made. Unskilled baselines fabricate with enthusiasm here — they convert "maybe a week" to "5 business days," invent CCB rosters ("PM, Sponsor, Tech Lead"), and auto-stamp "Approved" on a request that was merely submitted. This skill refuses all of that.
[TBD — user said "maybe a week"] marker in the structured slot. Do NOT convert to 5 days or $3,000.[TBD — CCB roster not stated]. Do not default-fill "PM, Sponsor, Tech Lead."Submitted | Under Review | Approved | Rejected | Deferred | Withdrawn. Unless the user explicitly stated a decision, disposition is Submitted and the approval block is empty. Never stamp Approved based on tone.user_estimate field. The structured numeric fields (schedule_impact_days, cost_impact_usd) stay null/TBD until the user gives a single value.options_considered is an empty array. Do not manufacture a fake "Option B: do nothing" unless the user said it.python3 scripts/create_change_request.py --output "<dir>/<ProjectName>_CR_<id>.docx" <<'JSON'
{ ...schema... }
JSON
Script produces a .docx with fixed section order: Header → Request Summary → Description & Justification → Impact Analysis (scope/schedule/cost/resources/quality/risk) → Options Considered → Recommendation → CCB / Approvals → Disposition & Baseline Version → Appendix (Draft Gaps).
{
"header": {
"cr_id": "string (e.g., CR-0007)",
"cr_title": "string",
"project_name": "string",
"requestor": "string",
"project_manager": "string or [TBD]",
"sponsor": "string or [TBD]",
"date_submitted": "YYYY-MM-DD",
"current_baseline_version": "string (e.g., v1.0)"
},
"category": "Scope | Schedule | Cost | Quality | Resource | [TBD]",
"priority": "Low | Medium | High | Critical | [TBD]",
"description": "string — what is being requested, in user's words",
"justification": "string — why, in user's words",
"impact": {
"scope": "string or empty",
"schedule_impact_days": "integer or null",
"schedule_user_estimate": "string or empty (verbatim fuzzy phrase)",
"cost_impact_usd": "number or null",
"cost_user_estimate": "string or empty (verbatim fuzzy phrase)",
"resources": "string or empty",
"quality": "string or empty",
"risk": "string or empty"
},
"options_considered": [
{"option": "string", "pros": "string", "cons": "string"}
],
"recommendation": "string or [TBD]",
"ccb_members": ["string — names user provided"],
"approvals": [
{"name": "string", "role": "string", "decision": "Approve | Reject | Defer | Pending", "date": "YYYY-MM-DD or empty"}
],
"disposition": "Submitted | Under Review | Approved | Rejected | Deferred | Withdrawn"
}
Notes:
schedule_impact_days is an integer ONLY if the user gave a precise number of days. Otherwise leave null and put the verbatim phrase in schedule_user_estimate.cost_impact_usd same rule — null unless the user gave a specific dollar figure.approvals is empty unless the user said "X approved" or "Y rejected." Listing CCB members is separate from listing decisions.disposition == "Approved" the script increments the baseline version and records the new version; otherwise the baseline stays put.User: "Need a change request for Project Aurora. Marcus is asking to add mobile push notifications to the MVP. He says it'll take maybe 2 weeks of Jen's time and probably a few thousand dollars in Firebase costs. We haven't gone to the CCB yet — just drafting. Ken PM, Mei Tanaka sponsor. Current baseline v1.2. Marcus reports to Raj."
Correct JSON:
{
"header": {
"cr_id": "[TBD — no CR ID stated]",
"cr_title": "Add mobile push notifications to MVP",
"project_name": "Project Aurora",
"requestor": "Marcus",
"project_manager": "Ken",
"sponsor": "Mei Tanaka",
"date_submitted": "[TBD]",
"current_baseline_version": "v1.2"
},
"category": "Scope",
"priority": "[TBD]",
"description": "Add mobile push notifications to the MVP",
"justification": "[TBD — requestor did not state justification]",
"impact": {
"scope": "Adds mobile push notification feature to MVP",
"schedule_impact_days": null,
"schedule_user_estimate": "maybe 2 weeks of Jen's time",
"cost_impact_usd": null,
"cost_user_estimate": "probably a few thousand dollars in Firebase costs",
"resources": "Jen",
"quality": "",
"risk": ""
},
"options_considered": [],
"recommendation": "[TBD]",
"ccb_members": [],
"approvals": [],
"disposition": "Submitted"
}
Note: Raj is NOT in CCB or approvals. Jen is a resource (named by requestor). "2 weeks" stays as text — NOT converted to schedule_impact_days: 10. "A few thousand dollars" stays as text — NOT converted to cost_impact_usd: 3000. Disposition is Submitted because the user said "haven't gone to the CCB yet." Baseline version does NOT increment.
Change control is the formal process for altering a baseline (scope, schedule, cost, or quality). The Change Control Board (CCB) is the governance body that dispositions each request. Project+ emphasizes that change requests preserve baseline integrity: nothing moves until a formal disposition is recorded. This skill enforces that structurally — the baseline version field is bound to the disposition field, so the artifact itself cannot claim a baseline shift that wasn't approved.