This skill should be used when the user wants a phased roadmap or timeline of a cogni-consult engagement's own WBS deliverables — sequenced from the dependency graph and durations and written as an Obsidian-browsable markdown artifact. Trigger on: "project plan", "engagement timeline", "roadmap", "show the roadmap", "gantt", "gantt chart", "schedule the engagement", "when does the engagement finish", "plan the timeline", "render the project plan", or when a WBS/dashboard view hands off a request for the sequenced plan — even if the user doesn't say "project plan" explicitly. This is an INTERNAL engagement-management view (a read-mostly sibling of consult-dashboard and consult-resume), not a client-facing content producer. Double Diamond phase phrasing ("discover phase", "deliver phase timeline") refers to a legacy engagement model no longer in the ecosystem; cogni-consult engagements have no phases — the roadmap phases here are the derived topological layers of the deliverable graph, not engagement stages.
How this skill is triggered — by the user, by Claude, or both
Slash command
/cogni-consult:consult-project-planThis skill is limited to the following tools:
The summary Claude sees in its skill listing — used to decide when to auto-load this skill
Render a phased roadmap of the engagement's work-breakdown structure — when each
Render a phased roadmap of the engagement's work-breakdown structure — when each
deliverable can start, how much effort it carries, who owns it, which points are
milestones, and which deliverables sit on the critical path — as a persisted
project-plan.md markdown artifact at the engagement root. It is the timeline
sibling of consult-dashboard (visual status) and consult-resume (next-action
recommender): a read-mostly view that turns the deliverable graph plus the
scheduling fields into a sequenced plan a consultant can browse in Obsidian.
Schedule lives on each deliverable inside its field.json entry — the five
optional scheduling fields start_date, due_date, duration, owner,
milestone (see $CLAUDE_PLUGIN_ROOT/references/project-plan-model.md). A phased
timeline is derived, never stored: the roadmap phases are the topological
layers of the depends_on[] graph (layer 0 = deliverables with no in-plan
dependency; layer N = deliverables whose dependencies all sit in layers < N), and
the duration-weighted forward pass + critical path come from
deliverable-graph.py <engagement-dir> schedule. This skill only reads that state
and writes project-plan.md; it never mutates a field.json, never writes a
duration-derived date back into engagement state, and never edits a deliverable's
schedule. Populating the scheduling fields is the job of consult-action-fields
(the plan-editing surface), not this skill.
When arriving via an in-session handoff that already resolved the engagement directory, skip discovery. Otherwise locate the engagement:
bash $CLAUDE_PLUGIN_ROOT/scripts/discover-projects.sh --json
Confirm the intended engagement with the user when more than one is registered.
When discovery returns zero engagements, treat it the same as a missing
consult-project.json.
Read <engagement-dir>/consult-project.json and branch explicitly:
Skill("cogni-consult:consult-setup") and stop — write nothing. Setup owns
scaffolding and the knowledge-base binding.workflow_state.scope is not "complete": redirect — "Scoping isn't closed
yet — the action fields and their deliverables come from consult-scope." —
then dispatch Skill("cogni-consult:consult-scope") and stop — write nothing.
There is no plan to render until scoping has named the fields and their
deliverables.Store the resolved engagement directory path and the engagement slug, name,
and language (for the artifact frontmatter). Everything below reads state only.
Run the duration-weighted schedule read first — it is also the cycle gate:
python3 $CLAUDE_PLUGIN_ROOT/scripts/deliverable-graph.py <engagement-dir> schedule
"success": false (a cycle in the deliverable graph makes layering and the
forward pass undefined), stop and surface the error — report the cycle from
data.cycles and do not write project-plan.md. A partial plan over a
cyclic graph would be misleading. Recommend the user resolve the cycle (fix the
offending depends_on[] edge via consult-action-fields) and re-run."success": true, keep data.schedule[] (per-deliverable
{key, action_field, deliverable, duration, earliest_start, earliest_finish, unscheduled}), data.critical_path[] (ordered keys on the longest
duration-weighted chain), data.project_earliest_finish (effort-days), and
data.unscheduled[] (keys with no valid non-negative authored duration).The schedule read does not emit owner, start_date, due_date, or
milestone — read those from state. For each action field listed in
consult-project.json's action_fields[], read
<engagement-dir>/action-fields/<slug>/field.json and collect, per deliverable
entry: its slug, title, depends_on[] (each an {action_field, deliverable}
WBS coordinate), and the scheduling fields owner, start_date, due_date,
milestone. The deliverable's schedule key is <action_field_slug>/<deliverable_slug>
— join it to the matching data.schedule[] entry by that key.
Surface any field.json that fails to parse as a warning alongside the plan
rather than aborting — a plan over the readable fields is still useful. (An
unreadable field means its deliverables are absent from the schedule read too.)
Compute each deliverable's plan layer from the depends_on[] edges collected in
Step 2. The schedule read has already confirmed the graph is acyclic, so
layering is well-defined:
K be the set of all deliverable keys <action_field>/<deliverable> read
in Step 2. For each deliverable, its in-plan dependencies are the
depends_on[] entries whose <action_field>/<deliverable> key is in K
(ignore any edge pointing outside the plan).layer(k) = 0 when the deliverable has no in-plan dependency; otherwise
layer(k) = 1 + max(layer(d)) over its in-plan dependencies. This is the
deliverable's earliest phase — every deliverable in a layer can begin once its
upstream layers complete.N-1 (Phase 1
= layer 0). Within a phase, order deliverables by earliest_start, then by key
for a deterministic tie-break.A deliverable is on the critical path iff its key is in data.critical_path[].
A deliverable is a milestone iff its field.json milestone is true — a
milestone anchors a checkpoint at its phase boundary. A milestone's only rendered
effect is the ◆ marker in the table's Milestone column and the milestone tag
on its gantt task; it does not alter layering or a deliverable's phase assignment.
Empty plan (scope complete, zero deliverables). A scoped engagement can still
carry no deliverables — Step 2 then reads an empty set and schedule returns empty
arrays. In that case still write project-plan.md (frontmatter with phase_count: 0), but in place of phase tables add one line noting the plan is empty until the
action fields declare deliverables, and point the user at consult-scope /
consult-action-fields. Skip the Mermaid block (no durations exist).
project-plan.mdWrite <engagement-dir>/project-plan.md (overwriting any prior run — the plan is
derived-at-read-time, so a re-render always reflects current state). Use this
shape:
YAML frontmatter (Obsidian-browsable):
---
type: project-plan
engagement: <slug>
engagement_name: <name>
lang: <language>
generated: <YYYY-MM-DD> # today's date
project_earliest_finish: <data.project_earliest_finish> # effort-days
phase_count: <number of layers>
critical_path: [<key>, ...] # data.critical_path verbatim, [] when empty
unscheduled_count: <len(data.unscheduled)>
---
Body — a short lead-in sentence (in the interaction language; see Important
Notes), then one ## Phase N heading per layer, each with a table:
| Deliverable | Action field | Owner | Start | Due | Duration (d) | Milestone | Critical path |
|---|
title (fall back to its slug).field.json owner / start_date / due_date,
or — when absent.duration (effort-days); render — for a
deliverable in data.unscheduled[] (no valid estimate), and 0 for an authored
zero.◆ when milestone is true, else blank.● when the key is in data.critical_path[], else blank.After the phase tables, add a one-line Summary: project earliest finish
(project_earliest_finish effort-days), the critical-path deliverable count, and
the number of unscheduled deliverables (so the reader knows how much of the plan is
estimated).
Optional Mermaid gantt block (emit only when at least one deliverable
carries a duration, i.e. data.unscheduled[] does not cover every deliverable;
omit the whole block gracefully, with a one-line note that no durations are
authored yet, when none do):
```mermaid fenced gantt with dateFormat YYYY-MM-DD and
axisFormat %Y-%m-%d, one section Phase N per layer, in phase order.start_date across all
deliverables, or — when none is authored — today's date, noting in the lead-in
that dates are a relative baseline derived from the topological order.start_date when present, else
anchor + earliest_start days (laying durations along the topological order, as
the read-model describes); length is its authored duration in days
(<duration>d), or 1d for an unscheduled/zero deliverable so the bar renders.
Tag critical-path tasks crit and milestone tasks milestone./ → _).The full scheduling-field schema, the roadmap read-model, and the schedule
envelope live in $CLAUDE_PLUGIN_ROOT/references/project-plan-model.md — cite it
rather than restating it.
Tell the user (in the interaction language) that the plan was written to
<engagement-dir>/project-plan.md, and give a one-line takeaway: the phase count,
the project earliest finish in effort-days, and — when any exist — how many
deliverables are still unscheduled (a prompt to set durations via
consult-action-fields for a sharper timeline). Do not open a browser; the
artifact is markdown for Obsidian.
project-plan.md
from field.json schedule fields and the schedule read; it never modifies a
field.json, consult-project.json, or any deliverable's schedule. Populating
the five scheduling fields is consult-action-fields' job.depends_on[] and durations, so project-plan.md is
always overwritten to match state. No phase number or derived date is ever
written back into engagement state.language field, which is the deliverable axis (it controls the
artifact's lang frontmatter, not how you address the user). Technical terms,
skill names, and CLI commands remain in English. See
$CLAUDE_PLUGIN_ROOT/references/interaction-language.md.Guides completion of development work by verifying tests, detecting environment, and presenting structured options for merge, PR, or cleanup.
Enforces test-driven development: write failing test first, then minimal code to pass. Use when implementing features or bugfixes.
Guides creation and editing of skills using test-driven development with pressure scenarios and subagents to verify agent compliance.
npx claudepluginhub cogni-work/insight-wave --plugin cogni-consult